Construction Notice for Building Rooftop Waterproofing Project

Construction Notice for Building Rooftop Waterproofing ProjectImage

Project details are as follows:
Work Scope: Buildings A, C, D, and Wuling Village 1
Construction Period: Starting January 5, 2026 (Estimated duration: 155 days)
Estimated Completion Date: June 8, 2026
Working Hours: 8:00 AM–5:00 PM daily

⚠️ Note:
The actual progress may be affected by weather conditions or material supply. Any schedule adjustments will be announced separately.

🏗️ Safety Reminder:
• Unauthorized personnel are prohibited from entering the rooftop construction areas.
• During lifting operations, please do not stay or pass through the restricted zones.

Thank you for your understanding and cooperation.